City Public Parking Garage at Plaza Centro Project

31 - City Public Parking Garage at Plaza Centro

Location:  Broadway and Toole City Public Parking Garage at Plaza Centro
Status:  Completed
Total Estimated Project Cost:  $6,675,000
Expenditures to Date 
Through 10/31/2011:
  $6,459,377
Estimated date of 
completion as of 12/1/2010:
  8/31/2011
Project Contact:  Chris Leighton
Description:  Design and construct City owned, Parkwise operated 400 stall public parking garage on city-owned land west of Union Pacific right of way, east of Toole, between Broadway and 4th Av.
Additional Info:  Mayor and Council adopted resolution 21313 on June 9, 2009 approving and authorizing a development agreement between the City of Tucson and OT Kino, LLC for development of the Plaza Centro project on two currently city owned parcels on either side of Toole between Broadway and 4th/Congress. The agreement requires the City of Tucson to design and construct a public parking garage on the property as a precondition to the developer purchasing the land and starting his mixed-use, high density, pedestrian oriented development. The City garage will be integrated into the overall development, meeting public parking needs in the area, including those of the Plaza Centro development.
Designation(s):  City of Tucson, Rio Nuevo District, Downtown, Capital Improvement Project
Last Update:  Tuesday Nov. 15, 2011

View this project on the Projects Map

Project Details

Updates

Project Status

  • Friday September 9, 2011
    Garage opened 9/8/11. Now completing punch list items.
  • Thursday August 4, 2011
    Grand opening 9/8/2011.
  • Thursday December 2, 2010
    Under Construction, Scheduled to open by 8/31/11
  • Friday October 1, 2010
    Ground Breaking Ceremony held October 1, 2010.
  • Tuesday September 7, 2010
    Final environmental study in process. Permit and condo plat in final review.
  • Thursday August 5, 2010
    Final envioronmental study in process.
  • Thursday July 1, 2010
    Design continues; working toward finalizing condominium plat documents to enable construction financing.
  • Monday May 3, 2010
    Environmental clean-up nearing completion
  • Tuesday April 6, 2010
    Schematic design complete. Projected design and construction costs indicate the garage will be self sufficient. Final site environmental cleanup in process. Full design and construction await Mayor and Council approval of financing and placement of financing.
  • Monday February 1, 2010
    Awaiting cost estimate for cleanup of assay office area, Design Review Board provided constructive feedback and input, Schematic design completed awaiting City direction to continue design.
  • Friday October 30, 2009
    Archeology testing on parcel 1 confirmed research of prior site uses and showed need for documentation of findings. Budget increased accordingly. Parcel 2 archeology rescheduled to much later in the project to enable continuous use of public parking on the parcel. Parking garage is in schematic design; construction contracting is in progress.